Measure E Funding Takes Care of CCUSD Repairs

Measure E funds have been taking care of repair issues for the Culver City Unified School District. A recap for the first semester of this school year was included in  the Assistant Superintendent of Business Services Santhasundari Rajiv’s report on Measure E at the School Board meeting

Projects moved into the ‘done’ column include completion of HVAC replacement at CCHS, Farragut and El Rincon, and the completion of the metal shade structure at CCHS. Complications included re-routing a sewer line that was in conflict with the ‘footing’ on the shade, and the project was completed later in December than originally scheduled. 

For details on updates at each of the schools and specifics on construction, please click on the Report on Measure E

 